Planner feature

Holidays and Time Off in Jira: Vacations, Leave and Approvals

ActivityTimeline puts public holidays, vacations, days off and sick leave on the same Planner as your Jira work. Every absence lowers that person's available capacity, so you see who is really free before you promise a date.

30-day free trial on the Atlassian Marketplace.

Sample ActivityTimeline Planner week, Nov 23 to 27, 2026, in four steps. 1: the USA Office holiday scheme adds Thanksgiving Day for Tom Becker and Emma Clark; Lukas Weber in Berlin works. 2: Emma adds a Vacation on Wednesday and her available capacity drops. 3: a manager approves the vacation, which then counts toward her yearly allowance. 4: Emma's Friday is at 10 hours of 8, so PORT-131 moves to Lukas.

What Are Holidays and Time Off in ActivityTimeline?

Holidays and time off in ActivityTimeline are non-working events on a person's Planner timeline: Holiday, Vacation, Day Off and Sick Leave. Each one takes hours out of that person's available capacity, so the workload indicator under their name and the team plan update at once. Public holidays come from holiday schemes, filled in by country. Vacations can go through manager approval and count toward a yearly allowance.

ActivityTimeline is a capacity planning, resource management and time tracking app for Jira. Time off is part of its Planner module, and you can add it from the Workspace too.

Four types

Holiday, Vacation, Day Off and Sick Leave, plus leave types of your own built on them.

Full or partial

A Vacation or Day Off can take a whole day or a set number of hours.

Holiday schemes

One list of public holidays per country or office, for teams, Jira groups or single people, across several years.

Approval

Managers approve vacations; approval can also be switched on for days off.

Allowances

A yearly number of vacation days, for everyone or per person.

Reports

The Leave Report and the Events Report show who took what, and who approved it.

Emma Clark has 30 hours of regression testing over five 8-hour days. A full-day Holiday, Vacation, Day Off or Sick Leave on Wednesday marks the day out of office and leaves 7.5 hours a day on the other four days. A partial Vacation or Day Off of 4 hours leaves 4 hours of capacity on Wednesday.

Holiday

Full day. No approval and no allowance. Added by a holiday scheme or by hand.

Vacation

Full day or a number of hours. Approval can be required, and approved days use the yearly allowance.

Day Off

Full day or a number of hours. Approval is optional; no yearly allowance.

Sick Leave

Full day, for days away for medical reasons. No approval and no allowance.

What Can You Do with Time Off Tracking in Jira?

Set holidays once per office, let people request time off, approve it, and see every absence in capacity and in reports.

Public holidays by country, per office

Create a holiday scheme, pick a country and ActivityTimeline fills in its official holidays. Edit the list to match your company calendar, then apply it to a team, a Jira group or one person. Pick a country to try it.

A holiday scheme named USA Office holidays, with the country United States, applied to the USA Office team. It holds Veterans Day, Thanksgiving Day, Christmas Day, New Year's Day and Martin Luther King Jr. Day for November 2026 to January 2027.

See who took what, per person

The Leave Report sums vacations, days off and sick leave for a team and a period, with approved vacations shown apart. Export the Events Report to Excel for HR.

Leave Report for the Portal team, current quarter: Tom Becker 4 approved vacation days and 1 day off; Emma Clark 4 approved and 1 unapproved vacation day and 2 days of sick leave; Lukas Weber 3 approved vacation days and half a day off.

Approve vacations before they count

A vacation starts unapproved. A manager approves it, leaves it unapproved or deletes it, right from the Planner where the workload is visible. Once approved, it counts toward the yearly allowance and people without the right permission can't change it. Approval is a setting per event type, so you can also require it for days off.

Vacation allowances that follow your policy

Set vacation days per year for everyone, per person or in bulk. The vacation year starts on January 1 or on each person's start date, and only approved vacations use the allowance.

Half days and partial days off

A dentist at 3 pm doesn't need a full day. Enter the hours, and only those hours leave the person's capacity for that day.

Leave types of your own

Need parental leave or training days? Create your own event type based on Vacation, Day Off, Sick Leave or Holiday, with its own name and icon.

An email when time off changes

Notification schemes email the people you choose when a vacation or other event is created, updated, approved or deleted.

Pending requests at a glance

An approval filter in the Issue Panel lists the vacations, bookings and placeholders still waiting, so nothing sits unapproved for weeks.

How to Track Holidays and Time Off in Jira with ActivityTimeline

Three steps. An administrator sets up holidays once; after that, people and managers add time off from the timeline.

Step 1 · Set up holiday schemes

Create one scheme per country or office, let ActivityTimeline fill in the public holidays, and apply it to the right teams, Jira groups or people.

Step 2 · Add time off

Click a day on a person's timeline in the Planner or Workspace, or use the New Task button. Pick Vacation, Day Off or Sick Leave, set the dates and choose a full or partial day.

Step 3 · Approve and replan

Approve the request, then check the workload indicator. Red days show where work has to move before the person leaves.

The Create New Item dialog lists Jira Issue options and Events: Booking, Placeholder, Note, Day Off, Sick Leave, Vacation, Holiday and Overtime. With Vacation picked for Tom Becker on Friday, Nov 27, his Friday becomes out of office and PORT-214 needs 12 hours on Thursday, 4 hours over his capacity.

Full setup, including holiday schemes and vacation limits, is in the Help Center.

Time Off Management in the Help Center

How to Set Up Holidays and Leave in Bulk Across Countries

Nobody should click in 400 holidays by hand. Set up one holiday scheme per country, apply it to whole groups of people, and load leave from the HR system you already use.

Step 1 · One scheme per country

Create a scheme, pick the country and ActivityTimeline fills in its official public holidays. Add company days such as a summer shutdown, and keep 2026, 2027 and 2028 in the same scheme.

Step 2 · Apply it to a Jira group

Apply each scheme to the Jira group or ActivityTimeline team for that office, such as "USA Office" or "Berlin". One scheme covers everyone in the group, and you can still give a single person their own scheme, for example a remote employee in another country.

Step 3 · Mixed teams keep one plan

A Platform team with people in Austin, Berlin, London and Lisbon stays one team on the Planner. Each person gets their own office's holidays, so the team's available capacity for any week adds up correctly.

Step 4 · Allowances for everyone at once

Set the yearly vacation days for the whole company, then change them for many people in one go with bulk mode, for example to match one country's statutory minimum.

The Platform team has four people on four holiday schemes: Tom Becker on United States, Lukas Weber on Germany, Olivia Hughes on United Kingdom and Ana Costa on Portugal. In the week of Nov 23, 2026, only Tom is off on Thursday for Thanksgiving, so the team has 152 of 160 hours available. In the week of Dec 7, Ana is off on Tuesday for the Immaculate Conception. In the week of Dec 28, Olivia is off on Monday for the Boxing Day substitute holiday and everyone is off on Friday, Jan 1.

Sync time off from your HR system with the REST API

Most companies already approve leave in an HR system. ActivityTimeline's REST API lets your team push that leave into the Planner, so the HR tool stays the source of truth and resource managers still see real availability next to the Jira work.

Create, update and delete leave. Vacations, days off (including partial days in hours), sick leave and holidays on any person's timeline.

Already approved. Vacations approved in the HR system can arrive pre-approved, so nobody approves them twice.

Matched records. Store the HR system's record ID on each time-off event, so a change or cancellation updates the right event.

Read it back. Pull teams, users, availability and capacity into BI tools or your own reports.

Admin-controlled. The API stays off until an administrator turns it on, and a read-only token is available for reporting.

Moving from spreadsheets? Import past and planned leave from a CSV file in one go.

Example: one approved vacation from your HR system

POST /rest/api/1/event
  username     = <Jira account ID>
  eventTypeId  = <id of the Vacation type>
  eventTitle   = Vacation
  start        = 2026-12-21
  end          = 2026-12-24
  isApproved   = true
  extraLink    = HR-LEAVE-48213

This creates an approved vacation on the person's timeline and keeps the HR record ID, so a later update or deletion finds it. Field names as in the REST API documentation.

REST API documentation

When Do Teams Use Holidays and Time Off in ActivityTimeline?

Six moments when a resource manager, team lead or PMO needs absences on the plan, not in a separate spreadsheet.

Teams in several countries

A sprint that spans Thanksgiving in the US and a normal week in Berlin needs two holiday calendars. One scheme per office keeps each person's capacity right.

The December crunch

Half the team asks for the last two weeks of the year. Seeing every request on one timeline in November shows which release dates still hold.

Managers approving leave

Approve from the timeline where you already see the workload, instead of approving in one tool and replanning in another.

Someone calls in sick

Add Sick Leave for today and tomorrow. The person's days turn blue, and the work that was due there shows up as red on the days left, ready to move.

Appointments and half days

A four-hour partial day off keeps the rest of the day plannable, so a doctor's visit doesn't wipe a whole day from capacity.

Year-end leave review

HR and the PMO check approved and unapproved vacation days per person before balances reset, from one Leave Report per team.

Good to know

Time off lives in ActivityTimeline. It changes capacity, plans and reports there, and it doesn't create Jira issues.

Only approved vacations count toward the yearly allowance, and allowances apply to the Vacation type.

Approval is a setting per event type. Vacation, Day Off, Booking and Placeholder can each require it or not.

Deleting a holiday scheme also removes its holidays from everyone it was applied to.

Holiday schemes are set up in ActivityTimeline itself; the REST API adds and changes the time-off events. It allows up to 1,000 requests an hour, so plan large first loads in batches or use the CSV import.

How the work around an absence moves to other days depends on your workload calculation settings.

Holidays and Time Off FAQ

What resource managers, team leads, HR and Jira admins ask before they move leave tracking into Jira.

Still have a question?

Ask us in a 25-minute demo
Does Jira have a holiday calendar for planning?
Not one that plans around people. Jira lets a board mark non-working days for its sprint reports, but it has no per-person vacations, sick leave or approvals. ActivityTimeline adds holidays and time off to the Planner, and each absence lowers that person's available capacity.
How do public holidays get into ActivityTimeline?
Through holiday schemes. An administrator creates a scheme, picks a country so ActivityTimeline fills in its official public holidays, and edits the list if needed. The scheme then applies to teams, Jira groups or individual users, and one scheme can hold several years. For people in several countries, create one scheme per country and apply each to that office's Jira group or team.
Can managers approve vacation requests?
Yes. A vacation starts unapproved, whether the person or a manager creates it. A manager can approve it, leave it unapproved or delete it. Approved vacations count toward the yearly allowance, and people without the right permission can no longer change them.
How does time off change the plan?
A non-working event lowers the person's capacity for those days, and the workload indicator under their name updates straight away. With an 8-hour day, a full Day Off on Monday leaves 0 hours available that day. Depending on your workload settings, remaining work moves to the other working days.
Can someone take half a day off?
Yes. A Vacation or Day Off can be a full day or partial. For a partial day you enter the number of hours, and only those hours come off the person's capacity.
Can ActivityTimeline track vacation allowances?
Yes. You set a number of allowed vacation days per year for everyone and change it per person, one at a time or in bulk. The vacation year starts on January 1 by default, or on each person's start date. Balances only change when a vacation is approved.
Can we sync time off from our HR system?
Yes, through the ActivityTimeline REST API. An administrator turns the API on and creates a token; your integration then creates, updates and deletes vacations, days off, sick leave and holidays on people's timelines. Vacations can arrive pre-approved, and each event can store the HR system's record ID. Past leave can also come in from a CSV file.
How do I see who has taken time off?
Open the Leave Report in Reports. It sums vacations, days off and sick leave for each person in a team over the period you choose, with approved vacations shown separately. The Events Report lists every event with its approval status and who approved it, on screen or in Excel.

Plan Your Jira Work Around Real Availability

Try holidays, time off and approvals on your own Jira projects for 30 days, or see them with your team's calendar in a 25-minute demo.